April 2008:
Pouring foundation -- Collections Storage (yellow area) and footing for F/V Shenandoah in Maritime Gallery (left image, center)

Scheduled
for April:
Pin piles
Pouring foundation
Leveling existing
floor
Framing
April 2008:
Slab pour for Collections Storage (above) and beginning of demolition of old Beach Basket building (right)

May 5, 2008:
Aerial view of site; concrete poured and framing begins
Week of May 19, 2008:
Installation of framing for roof and walls

Week ofJune 2, 2008:
Framing of walls, roof of administration and collections areas, and entrance.


Week of August 25, 2008:
Aerial view of construction site, courtesy of Wade Perrow.

Week of September 26, 2008:
Siding and painting of exterior completed.